A project is six months into its nine-month projected duration. The project manager reports that the project is at least three months behind schedule because certain key stakeholders were
resistant to consequential changes due to the project.
What might have been done differently during project planning to avoid this situation?
A. Better execution of the Manage Stakeholder Engagement
process
B. Development of a stakeholder engagement assessment matrix
C. Creation of a comprehensive stakeholder register
D. Establishment of a more robust communications management plan
HINT: Which
among the answer choices represent activities that might be performed during the Planning Process Group?