You are managing a renovation project of a house that is to be completed at a budget of $100,000. Earned value analysis shows that so far you have completed 40% of the work and spent
$60,000.
How much more will it cost to complete the project if the cost performance remains unchanged?
A. $160,000
B. $149,254
C. $120,000
D. $89,254
HINT: Determining how
much more it will cost to finish the project is the ETC. Also, consider the cost performance, which will remain unchanged.