In a pharmaceutical project, human trials have been started. The CEO is thrilled about the success of the trials up to this point. She announces that the size of the patient pool for the trials
should double from the one originally planned and results tracked in the new system launching this week.
What should the project manager do first?
A. Ramp up production to match the demand of the CEO
B. Consider what might be included in a change request
C. Adjust the scope
baseline to reflect the increased trial size
D. Communicate the change in the scope to the project stakeholders
HINT: Does the project team have the approval to make changes?