You are about to start planning for a large and complex project. Due to the size of the project along with the regulatory and environmental considerations, the development of a detailed project
management plan will be critical.
As a starting point for initial project planning, what is the first thing you should do?
A. Conduct a project kick-off meeting to inform and engage stakeholders and gain commitment
B. Review the project charter to understand the high-level information
about the project
C. Begin the process of identifying stakeholders so they can be engaged as necessary for project planning
D. Share the project scope statement with the project team for a common understanding of project deliverables
HINT: The Initiating Process Group has been completed, and the Planning Process Group is about to begin.