You are managing a project to construct a bridge at a location that is highly regulated by multiple levels of government. You are in the process of developing a plan that will establish the
criteria and the activities for developing, monitoring, and controlling the schedule.
Which of the following should you gather to complete this process?
A. The charter, project management plan, estimation databases, and PMO templates
B. Government standards, the assumption log,
schedule management plan, and milestone list
C. The resource breakdown structure, lessons learned register, and scheduling methodology
D. The project scope statement, risk register, and project team assignments
HINT: You are performing the Plan Schedule Management process. Look for the inputs to this process.