A team member submits a draft of the requirements management plan to the project manager for a review. The project manager notices that one of the components included in the plan does not belong
there.
Which of the following components did the project manager most likely notice?
A. A process that describes how the project requirements will be prioritized
B. The metrics that will be used and the rationale for using them
C. A process that specifies how a project scope
statement will be prepared
D. How requirement activities will be planned, tracked, and reported
HINT: Which element should be included in the scope management plan and not the requirements management plan?