During an inspection of a project deliverable, the team detects the same defect in the deliverable that has already been identified during a previous inspection. The project manager is confused about how this could
have happened since a change request was approved to repair the defect. After discussing the issue with the team, the project manager learns that the team never implemented the approved change request.
What could have helped prevent this situation?
A. Holding an approved change requests review
B. Conducting a retrospective
meeting
C. Performing a root cause analysis
D. Creating a quality report
HINT: What can be done to ensure that all approved change requests were implemented as specified?