A project to construct an assembly line is nearly complete. The project manager closes procurements, shares the final project report, updates the lessons learned repository, and obtains feedback from the relevant stakeholders.
What should the project manager do next?
A. Provide final payment to the suppliers
B. Send a summary of how the final product achieved the business needs
C. Transfer the completed assembly line to operations
D. Send formal written notice to the vendors that the contracts have been completed
HINT: All but one of
the answer choices have already been completed in the scenario.