Two team members are arguing over how to organize the work packages in the work breakdown structure (WBS). One says the work packages should be arranged in the order the work is planned to
be carried out, while the other insists the order of the work packages in the WBS does not matter. The two ask the project manager for advice.
What is the project manager's best response?
A. Work is decomposed and sequenced in the Define Activities process.
B. Any approach is good as long as the team members avoid the conflict.
C. The chronological order of tasks is defined in the Sequence Activities process.
D. The approach should be defined by the project management office (PMO).
HINT: In what process are project activities sequenced?