You are part of a cross-functional development team piloting an adaptive approach to project management in an organization that has traditionally used a predictive approach. You realize that you
have to tailor the template of the schedule management plan.
Which of the following components of the template are you likely to tailor the most?
A. The rules of performance measurement, the
summary milestones, and the key deliverables
B. The organizational procedures links, the units of measure, and the project organization charts
C. The schedule model development, the release and iteration length, and the reporting formats
D. The project schedule model maintenance, the level of accuracy, and the level of precision
HINT: To eliminate some choices, look for items that
are not components of the schedule management plan.