You want to recognize the contributions of some of the high-performing team members so far in the project.
Which of the following do you need to guide you through this process?
A. Organizational process
assets
B. Stakeholder register
C. Project team assignments
D. Quality metrics
HINT: Which of the following is an input to the Manage Team process and specifies policies for certificates of appreciations, and other company's perks?