You are facing problems decomposing the testing work package into the final activities required to complete the work package.
Detailed testing plans and activities cannot be determined until the system is at least 50% developed and more details become available.
The system development work package will
take at least three months to complete.
What is the best way to resolve this problem?
A. Use
product analysis techniques such as product breakdown and systems analysis to decompose the system testing work package
B. Decompose the system development work package now and decompose the system testing work package later
C. Break down the project into multiple phases so that the system testing work package goes into the second project phase
D. Consult the project management plan to determine what to do in this situation
HINT: Which of the available choices describes rolling wave planning?