You are managing a project to build a house for a private client. A few weeks before the project's planned completion date, the client calls and asks to add an outdoor sauna to the property. You analyze the project schedule and determine
that this change would be fairly easy to implement without having an impact on the completion date.
What should you do first?
A. Begin construction since the project completion date is not violated
B. Review the requested change against all project constraints
C. Have the sponsor verify if the change violates construction regulations
D. Consult with the change control board on how to handle the change
HINT: You need to make sure you have everything you need to properly handle a change and understand its impacts on the project.