A project manager meets with a customer for initial discussions about an upcoming project. At the end of the meeting, the customer asks the project manager for a rough estimate of the project duration. Based on her experience with three similar projects, the project manager provides an estimate of 8-10
months.
What estimation technique does the project manager use?
A. Expert judgment
B. Three-point estimating
C. Analogous estimating
D. Bottom-up estimating
HINT: Identify the estimating technique that compares a project to a previous, similar project.