While reviewing your project's performance, you discover a significant variance. If the issue is not fixed before the next customer inspection, your project might be canceled.
However, after a further review conducted by the project team, you are glad to hear that bringing the project back on track requires only a minor correction to a configuration element.
What should you do first?
A. Implement the corrective action
B. Submit a change request
C. Consult the project sponsor
D. Delay the customer inspection
HINT: What is the proper change control procedure when an adjustment to a configuration element is required?